The original numbering of the claims must be preserved throughout the prosecution. When claims are canceled the remaining claims must not be renumbered. When claims are added, they must be numbered by the applicant consecutively beginning with the number next following the highest numbered claim previously presented (whether entered or not). When the application is ready for allowance, the examiner, if necessary, will renumber the claims consecutively in the order in which they appear or in such order as may have been requested by applicant.
[32 FR 13583, Sept. 28, 1967; revised, 62 FR 53131, Oct. 10, 1997, effective Dec. 1, 1997]
From the refusal of the primary examiner to admit an amendment, in whole or in part, a petition will lie to the Commissioner under § 1.181.